S::Select® system as ready-to-use “package” in a container

15.05.2020
Since the end of 2019 the wastewater treatment plant S (size 250,000 PE) is running a S::Select® system which was delivered completely prefabricated in a container. As the foundations and connections were already prepared, the plant could start operating within a few days and improvements in sludge settling speed, ISV, filterable substances and Pges were be achieved very soon.

Due to the stable and reliable process conditions that S::Select® has achieved for the wastewater treatment plant, further optimizations in the entire operational process are being tackled.
EssDe GmbH  |  Rietwiesstrasse 39  |  CH-8737 Gommiswald  |  SWITZERLAND  |  Phone +41 55 290 11 41  |  5inv+foi0@ed+ssi8dek..cu5omd